TOC3 Australia

From NOW to WOW in under 9 days 

BAE Systems Australia continues to break company record.

RAPID CCPM IMPLEMENTATION AND RAPID RESULTS USING EXEPRON - Andrew Kay

BAE Systems Australia implements Critical Chain Project Management to their Deep Maintenance Program of LIF Jets with amazing speed and equally amazing results.

 

AndrewBAE56

Presentation to the Exepron User Conference in Lafayette, Louisiana USA July 2015  Presentation Video

 

SummaryBAE

 

May 2015: 6 jets from 6, first time around on time and some up to 43% less time, a company record.

September 2015:  14 jets from 14, on time to requirement. The company record continues to tumble.

 

This is a remarkable result as the aircraft MRO environment is one of the most complex in which to deliver everything on time, to budget and to specification. What surprised BAE was the speed by which the knowledge and solution was delivered and successfully applied.

 

SimonM

 

The Critical Chain Project Management (CCPM) solution was fully installed in under 9 days.

First jet in project execution within 4 days, first results through the hangar within 2 weeks.

Some jets had up to 21% scope increase. 

 

TOC3 in collaboration with Danny Walsh, CEO of Exepron, provided the expert training and guided facilitation to the talented BAE team who quickly jumped on board with CCPM and grabbed onto EXEPRON with both hands. The software was used for both training, building the project networks in planning and runnning the Maintenance Program in real time.

 

Note: This is yet another TOC3 rapid implementation project where the solution was installed and operational within 10 days.

 

video

Exepron

exepron

Exepron is a unique multi-project Critical Chain Project Management Software solution with embedded real time intelligence to plan, schedule and execute projects.
Exepron answers the 7 most critical questions of project management in real time.
Contact us to find out how.

NEWS

PROJECT MANAGEMENT THAT DELIVERS30 DAY FREE TRIAL Synchronize 50 Projects 15 GB Storage Capacity Unlimited User Access Global Coll...
  ...

In a nutshell

“I have to spend less and less time on the factory floor trouble shooting and getting production to flow”“We have lots more capacity now that we are better organised and can schedule...
REAL RESULTS - Fast, Safe and SustainableSince the early 1990’s companies around the world including Australia and New Zealand have been achieving rapid and sustainable breakthrou...
\"That’s truly amazing” Commenting on >75% reduction of WIP in less than 3 weeks and total elimination of back orders. Grant Johnston: Managing Director, Best Bar Reinforcements, Me...
How do we go about helping you get these kinds of Real Results?We do it by getting you to see that in order to have a breakthrough in performance the rules of business have to change.Manufac...
We have had some dramatic changes to the business in recent years including new ownership. However, we are still running the same system you helped install - it just works!\" Paul Winterflo...
Maximise Profits with Throughput Accounting and the Theory of ConstraintsHow what you measure makes all the difference Are you achieving your financial targets?  Are you exper...
\"My team no longer need to come to me to know wh at to do, the boards show them”.  “Loading trucks and meeting delivery is now just so easy” Jessie: Afternoon Shift Foreman...
1. PROBLEM DEFINITION: Understand Environment and agree on Core Problem to solve (2 - 5 days)We understand your environment - site audit We get to meet your key people and you get to know&nb...
Integrity: Our word is our bond We do as we say We don\'t promise what we can\'t deliver and if for some reason we fail we apologise without delay and make goodOpenness We tell it...
The Goal – A Process of Ongoing ImprovementBy Dr. Eli GoldrattA new hero is winning the hearts and minds of American Managers.  The hero’s name is Alex Rogo, and thousands of executives...

Login Form



TOCICO

tocico_1

Certified Practitioners